Cost Management Plan โ€” Alliance Resilience Project

โ€ข16 min readโ€ข0 views

Confidentiality Level: NATO Confidential

Framework: PMBOKยฎ Guide (7th Edition)


Cost Management Plan

Project: Alliance Resilience Project

Project ID: 08bef030-8f72-4360-a3b0-dc0192bf4405

Version: 1.0

Date: 2025-04-10

Prepared By: Menno Drescher, Project Manager

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

1. Executive Summary

1.1 Purpose

The Cost Management Plan (CMP) for the Alliance Resilience Project establishes a structured framework for estimating, budgeting, monitoring, and controlling project costs in alignment with PMBOKยฎ Guide (7th Edition) principles. This plan ensures financial transparency, accountability, and value delivery by defining cost estimation methods, budget baselines, control processes, and performance measurement metrics. Given the projectโ€™s strategic importance to NATO Air Command, this document integrates the Uncertainty, Measurement, and Delivery Performance Domains to address cost-related risks, compliance requirements, and stakeholder expectations.

1.2 Project Overview

The Alliance Resilience Project aims to develop a modular Automated Diplomatic Protocol Automation (ADPA) system to streamline diplomatic clearances and asset relocations for VIP aircraft (e.g., Qatari 747-8) across NATO/EU hubs such as Lelystad and Schiphol. Key features include:

  • Predictive drift detection for militia threats (leveraging AI/ML models).
  • 48-hour airstrip orchestration via baseline extraction from NATOโ€™s Air Command and Control System (ACCS).
  • Need-to-know compliance logs for operational readiness.
  • Integration with EU Diplomatic Clearance Portal and NATO Threat Intelligence Databases.

The projectโ€™s success hinges on delivering 60% faster diplomatic clearance processing, 90% improved threat detection accuracy, and full operational readiness within 24 months (as outlined in the Business Case and Scope Management Plan).

1.3 Alignment with PMBOK 7th Edition

This CMP aligns with PMBOK 7โ€™s Performance Domains and Principles:

Performance Domain Alignment in CMP
Stakeholders Defines roles/responsibilities for NATO Air Command, EU Member States, and vendors.
Team Assigns cost ownership to the Finance Lead, Procurement Manager, and PM.
Development Approach Uses agile budgeting for iterative ADPA system development.
Measurement Implements Earned Value Management (EVM) with CPI/SPI targets.
Uncertainty Includes cost contingency reserves (10% for known risks, 5% for unknowns).
Delivery Links cost baselines to milestone-based funding (e.g., MVP, full deployment).
Project Work Integrates cost control with Integration Management Plan processes.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

2. Cost Overview

2.1 Cost Management Objectives

The primary objectives of cost management for the Alliance Resilience Project are:

Objective Description Success Metric Target Date
Accurate Cost Estimation Develop realistic cost estimates using historical data and expert judgment. ยฑ10% variance from final actual costs. 2025-06-30
Budget Adherence Ensure project execution stays within the approved budget baseline. โ‰ค5% cost variance (CV) at project completion. 2027-12-31
Value Delivery Optimize cost efficiency while maximizing operational resilience benefits. CPI โ‰ฅ 0.95; ROI โ‰ฅ 20% over 5 years (per Business Case). 2027-12-31
Risk-Responsive Budgeting Allocate contingency reserves for identified risks (e.g., vendor delays, scope changes). 100% coverage of high-probability/high-impact risks. 2025-07-31
Stakeholder Transparency Provide real-time cost reporting to NATO Air Command and EU Member States. Monthly cost reports delivered on time with โ‰ค2% data errors. Ongoing

2.2 Cost Constraints and Assumptions

Constraints

  1. Fixed Funding Sources: Budget is constrained by NATO Air Commandโ€™s annual allocation (โ‚ฌ25M) and EU grants (โ‚ฌ5M).
  2. Regulatory Compliance: Costs must align with NATO Financial Regulations and EU Public Procurement Directives.
  3. Timeline Pressure: MVP must be delivered by 2026-06-30 to meet operational readiness goals (per Project Charter).
  4. Vendor Dependencies: Third-party AI/ML vendors may introduce cost variability (e.g., model training, licensing).

Assumptions

  1. Labor Rates: NATO internal labor costs are fixed at โ‚ฌ120/hour for technical staff and โ‚ฌ90/hour for support staff.
  2. Exchange Rates: USD/EUR exchange rate is fixed at 1.10 for budgeting purposes.
  3. Inflation: Annual inflation rate of 2% is applied to long-term contracts.
  4. Vendor Stability: Third-party vendors will adhere to fixed-price contracts (per Procurement Manager).
  5. Scope Stability: No major scope changes after 2025-09-30 (per Scope Management Plan).

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

3. Estimation Methods

3.1 Cost Estimation Approach

The Alliance Resilience Project employs a hybrid estimation methodology combining analogous, parametric, and bottom-up techniques to ensure accuracy and stakeholder buy-in.

Method Description Tools Inputs Outputs
Analogous Uses costs from similar NATO projects (e.g., Kabul evacuation automation). Excel, NATO PMO Library Historical data from NATOโ€™s ACCS upgrades. High-level budget estimate (ยฑ25% accuracy).
Parametric Applies statistical models to estimate costs (e.g., cost per diplomatic clearance automated). COCOMO II, Jira Scope Management Plan (WBS), vendor quotes for AI/ML model training. Mid-level budget estimate (ยฑ15% accuracy).
Bottom-Up Aggregates detailed cost estimates for each WBS work package. Microsoft Project, Excel WBS Dictionary, labor rates, vendor contracts, hardware/software quotes. Detailed budget estimate (ยฑ5% accuracy).
Three-Point Uses optimistic, pessimistic, and most likely estimates to calculate a weighted average (PERT). Excel, Monte Carlo Simulation Expert judgment from Lead Architect and AI/ML Engineer. Risk-adjusted cost ranges.

3.2 Cost Estimation Process

  1. Define Scope: Align with Scope Management Plan (WBS, deliverables).
  2. Gather Data: Collect historical costs (NATO PMO Library), vendor quotes, and labor rates.
  3. Select Methods: Apply analogous for high-level estimates, bottom-up for detailed work packages.
  4. Validate Estimates: Review with Finance Lead and Procurement Manager.
  5. Document Assumptions: Record constraints, risks, and dependencies (e.g., vendor lead times).
  6. Obtain Approval: Submit to Change Control Board (CCB) for baseline approval.

3.3 Cost Estimation Outputs

Output Description Owner
Activity Cost Estimates Detailed cost breakdown for each WBS work package (e.g., AI model training: โ‚ฌ1.2M). Finance Lead
Basis of Estimates Documentation of assumptions, methods, and data sources. Project Manager
Cost Management Plan Updates Revisions to this CMP based on estimation findings. Project Manager

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

4. Budget Baseline

4.1 Budget Development Process

The cost baseline is developed by aggregating cost estimates from the WBS and adding contingency reserves for risks. The process includes:

  1. Aggregate Estimates: Sum costs for all work packages (e.g., software development, hardware procurement).
  2. Add Contingency Reserves:
  • 10% for known risks (e.g., vendor delays, scope changes).
  • 5% for unknown risks (e.g., geopolitical disruptions).
  1. Time-Phase Budget: Allocate costs to project phases (e.g., Inception: โ‚ฌ5M, MVP: โ‚ฌ12M, Full Deployment: โ‚ฌ8M).
  2. Obtain Approval: Submit to NATO Financial Compliance Team and CCB for sign-off.

4.2 Budget Breakdown

The table below outlines the approved budget baseline (โ‚ฌ30M total):

Category Estimated Cost (โ‚ฌ) Notes
Software Development 12,000,000 Includes AI/ML model training, ADPA system coding, and integration with NATO/EU systems.
Hardware Procurement 4,500,000 Servers, networking equipment, and redundancy systems for NATO hubs.
Vendor Contracts 3,000,000 Third-party AI/ML vendors, cloud hosting (AWS GovCloud).
Labor Costs 6,000,000 NATO internal staff (โ‚ฌ120/hour), consultants (โ‚ฌ150/hour).
Contingency Reserves 3,000,000 10% for known risks, 5% for unknowns.
Training & Change Management 1,500,000 End-user training for NATO Air Command Operations Team.
Total 30,000,000

4.3 Funding Sources

Source Amount (โ‚ฌ) Schedule Conditions
NATO Air Command 25,000,000 Quarterly allocations (2025-2027) Approved by NATO Financial Compliance Team; aligned with annual budget cycles.
EU Grants 5,000,000 Annual disbursement (2025-2026) Compliance with EU Public Procurement Directives; milestone-based payments.

4.4 Payment Schedule

Milestone Target Date Payment (โ‚ฌ) Funding Source Conditions
Project Kickoff 2025-05-01 3,000,000 NATO Air Command Signed contracts with vendors; approved WBS.
Inception Phase 2025-12-31 5,000,000 NATO Air Command Completion of system architecture; approved risk management plan.
MVP Delivery 2026-06-30 12,000,000 NATO + EU Grants Successful UAT; compliance with NATO Threat Intelligence Databases.
Full Deployment 2027-06-30 8,000,000 NATO Air Command Operational readiness; 95% user adoption.
Project Closure 2027-12-31 2,000,000 NATO Air Command Lessons learned documented; final audit completed.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

5. Control Processes

5.1 Cost Control Framework

The Alliance Resilience Project employs Earned Value Management (EVM) to monitor cost performance and trigger corrective actions. Key processes include:

Process Description Tools Frequency
Performance Measurement Track CPI, SPI, CV, and SV against baselines. Power BI, Microsoft Project Monthly
Variance Analysis Identify cost/schedule variances and root causes (e.g., vendor delays, scope changes). Excel, Jira Monthly
Corrective Actions Implement fixes (e.g., rebaselining, resource reallocation, scope adjustments). CCB, Risk Management Plan As needed
Reporting Provide cost reports to NATO Air Command and EU Member States. Power BI Dashboards Monthly

5.2 Variance Thresholds

Metric Target Threshold Action
CPI โ‰ฅ 0.95 < 0.90 Escalate to CCB; review scope and resource allocation.
SPI โ‰ฅ 0.95 < 0.90 Adjust schedule; fast-track critical path activities.
Cost Variance โ‰ค 5% > 10% Freeze non-critical spending; activate contingency reserves.
Schedule Variance โ‰ค 5% > 10% Reallocate resources; negotiate vendor deadlines.

5.3 Corrective Actions

Variance Type Possible Causes Corrective Actions Owner
Cost Overrun Vendor delays, scope changes, inflation - Rebaseline budget with CCB approval. - Reallocate resources from non-critical tasks. Project Manager
Schedule Delay Resource shortages, technical challenges - Fast-track critical path activities. - Add overtime or temporary staff. Technical Lead
Underutilized Budget Overestimation, scope reduction - Reallocate funds to high-risk areas. - Accelerate training or testing phases. Finance Lead

5.4 Cost Control Tools

Tool Purpose Owner
Microsoft Project Track cost baselines, milestones, and dependencies. Project Manager
Power BI Visualize cost performance (CPI, SPI, CV, SV) in real-time dashboards. Finance Lead
Jira Monitor agile sprint costs and vendor deliverables. Development Team
Excel Conduct variance analysis and generate cost reports. Finance Lead

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

6. Earned Value Management (EVM)

6.1 EVM Metrics

Metric Formula Target Measurement Method Frequency
Cost Performance Index (CPI) EV / AC โ‰ฅ 0.95 Compare Earned Value (EV) to Actual Cost (AC). Monthly
Schedule Performance Index (SPI) EV / PV โ‰ฅ 0.95 Compare Earned Value (EV) to Planned Value (PV). Monthly
Cost Variance (CV) EV - AC โ‰ค 5% Difference between Earned Value and Actual Cost. Monthly
Schedule Variance (SV) EV - PV โ‰ค 5% Difference between Earned Value and Planned Value. Monthly
Estimate at Completion (EAC) BAC / CPI โ‰ค โ‚ฌ30M Forecasted total cost at project completion. Quarterly

6.2 EVM Reporting

Report Audience Frequency Content
Monthly Cost Report NATO Air Command, EU Member States Monthly CPI, SPI, CV, SV, EAC, variance analysis, corrective actions.
Quarterly Audit NATO Financial Compliance Team Quarterly Budget reconciliation, contingency reserve usage, compliance with NATO Financial Regulations.
CCB Review Change Control Board As needed Major variances (>10%), rebaselining requests, risk mitigation strategies.

6.3 EVM Example (Inception Phase)

Metric Value Status
Planned Value (PV) โ‚ฌ5,000,000 On track.
Earned Value (EV) โ‚ฌ4,800,000 4% behind schedule (SV = -โ‚ฌ200,000).
Actual Cost (AC) โ‚ฌ5,100,000 2% over budget (CV = -โ‚ฌ300,000).
CPI 0.94 Below target (0.95); activate corrective actions.
SPI 0.96 Above target (0.95); no immediate action required.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

7. Roles and Responsibilities

7.1 Cost Management Roles

Role Responsibilities Contact
Project Manager Overall cost management, budget approvals, variance analysis, reporting to NATO Air Command. menno.drescher@placeholder.local
Finance Lead Cost estimation, budget development, funding coordination, financial reporting. finance.lead@placeholder.local
Procurement Manager Vendor negotiations, contract management, payment scheduling. procurement.manager@placeholder.local
Technical Lead Resource allocation, tool/license cost tracking, technical cost optimization. technical.lead@placeholder.local
Lead Architect Validate cost estimates for system architecture and integration. lead.architect@placeholder.local
AI/ML Engineer Estimate costs for AI model training and predictive analytics. ai/ml.engineer@placeholder.local
NATO Financial Compliance Team Conduct quarterly audits, ensure compliance with NATO Financial Regulations. nato.financial.compliance.team@placeholder.local
Change Control Board (CCB) Approve budget rebaselining, major cost variances, and contingency reserve usage. change.control.board.(ccb)@placeholder.local

7.2 RACI Matrix for Cost Management

Activity PM Finance Lead Procurement Manager Technical Lead CCB
Cost Estimation A R C C I
Budget Development A R C C I
Contingency Reserve Allocation A R C C A
Variance Analysis R A C C I
Corrective Actions R C C C A
Cost Reporting R A C C I

Key:

  • R = Responsible
  • A = Accountable
  • C = Consulted
  • I = Informed

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

8. Risk Management

Risk Probability Impact Mitigation Strategy Owner
Vendor Cost Overruns High High - Use fixed-price contracts for 80% of vendor work. - Include penalties for delays. Procurement Manager
Scope Creep Medium High - Enforce CCB approval for all scope changes. - Conduct monthly scope reviews. Project Manager
Exchange Rate Fluctuations Medium Medium - Hedge 50% of USD-denominated contracts. - Include 10% buffer in budget. Finance Lead
Resource Shortages High High - Cross-train staff. - Maintain contingency hiring plan. Technical Lead
Regulatory Compliance Costs Medium High - Engage Compliance Officer early. - Allocate 5% contingency reserve for compliance risks. Compliance Officer
AI/ML Model Training Delays High Medium - Use pre-trained models where possible. - Include milestone-based payments for vendors. AI/ML Engineer

8.2 Risk Monitoring

  • Monthly Risk Reviews: Conducted by the Project Manager and Finance Lead.
  • Quarterly Risk Audits: Performed by the NATO Financial Compliance Team.
  • Trigger-Based Reviews: Activated if CPI < 0.90 or CV > 10%.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

9. Compliance and Standards

9.1 Regulatory Compliance

The Alliance Resilience Project adheres to the following standards:

Standard Requirement Owner
NATO Financial Regulations Budget approvals, audit trails, and financial reporting. NATO Financial Compliance Team
EU Public Procurement Directives Competitive bidding for contracts >โ‚ฌ139,000. Procurement Manager
ISO 21500 (Project Management) Alignment with cost management guidelines. Project Manager
GAAP (Generally Accepted Accounting Principles) Financial reporting and budgeting compliance. Finance Lead
NATO Security Regulations Protection of classified cost data (e.g., vendor contracts). Compliance Officer

9.2 Organizational Policies

  • NATO Cost Coding: All expenses must use NATOโ€™s standardized cost codes (e.g., 5000 for Software Development).
  • Approval Workflows: Budget changes >โ‚ฌ50,000 require CCB approval.
  • Vendor Selection: Must follow NATOโ€™s Vendor Qualification Process.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

10. Funding Requirements

10.1 Funding Sources and Schedule

See Section 4.3 for funding sources and schedule (NATO Air Command: โ‚ฌ25,000,000; EU Grants: โ‚ฌ5,000,000).

10.2 Payment Terms

  • NATO Air Command: Payments released within 30 days of milestone completion.
  • EU Grants: Payments released within 60 days of compliance reporting.
  • Vendors: 30% upfront, 40% at MVP, 30% at project closure (per Procurement Manager).

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

11. Cost Management Process Flow

graph TD
    A[Estimate Costs] --> B[Determine Budget]
    B --> C[Control Costs]
    C --> D[Report Performance]
    D --> E[Review and Adjust]
    E --> A
    A -->|Inputs: WBS, Historical Data| F[Activity Cost Estimates]
    B -->|Inputs: Cost Estimates, Reserves| G[Cost Baseline]
    C -->|Tools: EVM, Power BI| H[Variance Analysis]
    D -->|Outputs: Monthly Reports| I[Stakeholder Updates]
    E -->|Outputs: Rebaselining| B

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

12. Appendices

Appendix A: Cost Estimation Templates

  • WBS Cost Estimation Template (Excel)
  • Vendor Quote Comparison Template (Excel)
  • Contingency Reserve Calculation Template (Excel)

Appendix B: Historical Data

  • NATO ACCS Upgrade Costs (2020-2023)
  • Kabul Evacuation Automation Costs (2021)

Appendix C: Vendor Quotes

  • AI/ML Model Training (Vendor: DeepMind Technologies)
  • Cloud Hosting (Vendor: AWS GovCloud)

Appendix D: Glossary

  • Cost Baseline: The approved time-phased budget for the project, including contingency reserves.
  • Contingency Reserve: Budget allocated for identified risks (known unknowns).
  • Management Reserve: Budget allocated for unidentified risks (unknown unknowns).
  • Earned Value (EV): The value of work performed expressed in terms of the approved budget.
  • Planned Value (PV): The authorized budget assigned to scheduled work.
  • Actual Cost (AC): The realized cost incurred for the work performed.

โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€

13. Approval

Name Role Signature Date
Menno Drescher Project Manager
[Finance Lead Name] Finance Lead
[NATO Air Command Rep] NATO Air Command Representative
[EU Grant Coordinator] EU Grant Coordinator

Document Control

  • Version History:
    • 1.0: Initial draft (2025-04-10).
  • Change Log: Tracked in NATO PMO Library.
  • Distribution: NATO Air Command, EU Member States, CCB, Finance Lead.